Construction Cost Index for collectively built one- or two-dwelling buildings
Wage drift and VAT excluded
Collectively built one- or two-dwelling buildings | 2024 | 2025 | ||||||
---|---|---|---|---|---|---|---|---|
Type of costs | May | Dec | Jan | Feb | Mar | Apr | May | |
Materials | 159.1 | 159.9 | 161.7 | 162.8 | 163.0 | 165.1 | 166.0 | |
Labour, wage drift excluded | 123.5 | 123.5 | 123.6 | 123.6 | 123.6 | 123.6 | 127.8 | |
Plant and equipment | 135.0 | 133.7 | 133.7 | 133.8 | 133.8 | 133.8 | 134.0 | |
Transport, energy | 135.2 | 134.6 | 136.2 | 136.6 | 134.0 | 133.4 | 132.7 | |
Contractor's other costs | 133.1 | 133.4 | 133.8 | 133.8 | 134.3 | 133.7 | 135.5 | |
Contractor's costs (1–5) | 140.3 | 140.5 | 141.4 | 141.9 | 141.9 | 142.6 | 144.5 | |
Clients other costs | 180.0 | 164.1 | 164.0 | 163.8 | 164.2 | 163.6 | 167.1 | |
Total Construction cost index (1–6) | 148.0 | 145.1 | 145.8 | 146.1 | 146.2 | 146.6 | 148.9 |